$10 Million In Prosper Road Work Starts Early 2027

Prosper approved $10 million for Dallas Parkway and Frontier Parkway road work that starts in late January or early February.
Frontage road rebuilt with flex base beside a tollway overpass under construction in a North Texas suburb.

Prosper approved a $10 million road contract on October 27, and the schedule puts crews on Dallas Parkway and Frontier Parkway in late January or early February. For Collin County sitework and utility contractors, it is a four-month window of frontage road repair, underpass work, base and haul off on one of the busiest growth corridors in North Texas.

The Dallas North Tollway keeps pushing north, and the towns along it are getting their local roads ready for it. Prosper’s latest contract is a good example.

The situation

The Prosper Town Council approved a $10 million construction contract at its October 27 meeting. Of that, $7.2 million is for repairs to the northbound Dallas Parkway frontage road near First Street, Prosper Trail and Frontier Parkway. The other $2.8 million is for Frontier Parkway improvements at the future tollway underpass. With design and materials testing contracts, the two projects total about $7.5 million and $2.9 million (Source: Community Impact, October 30, 2026).

The schedule

Construction is expected to start in late January or early February 2027 and run about 120 days, finishing ahead of the tollway extension opening in 2027.

$10 million in Prosper road work starts in early 2027.

Community Impact · October 30, 2026

What the work needs

Frontage road repair is a full-depth job in places: pavement removal and haul off, subgrade repair, new base, then paving. Underpass approaches need fill, base and drainage, often with tight access and traffic control.

Haul off for removed pavement and unsuitable subgrade.

Flex base or crushed concrete base under the new pavement.

Select fill for approaches and grade changes.

Bedding and backfill for drainage and utility adjustments.

What to do with it

The prime contract is awarded, so the opportunity is the work around it: removal and haul off, utilities, drainage and supply. Make contact before mobilization. Plan for a steady delivery rate across 120 days, not one big push. And plan the corridor: Collin County growth along the tollway means many crews pulling from the same yards in the same months. We have written about that demand before. When you are ready, request a delivered quote.

A 120-day schedule runs on steady trucks.

Call 214-282-7980 or request a quote at aggregatesnow.com.

Ready to Order

Get a Delivered Number Before You Lock the Budget

One call covers sourcing, trucking and the delivery schedule. 24-hour quote response.

Delivered Pricing

Need a Delivered Number This Week?

Material, trucks and the delivery schedule in one call. 24-hour quote response.

214-282-7980Request a quote online

Run the Numbers

Materials Calculator

Work out tons and loads before you call.

Use the Calculator

Market Intelligence

Get the Weekly Brief

Market updates, material availability, and Texas construction intel. Published weekly for contractors.

Market Intelligence

Get the Weekly Brief

Texas construction and material market updates for contractors. One email, Wednesday mornings.