The Dodge Momentum Index tracks nonresidential building projects entering planning, and it leads actual construction spending by twelve to eighteen months. September’s reading splits cleanly in two. Institutional planning rose 17.2 percent over the year. Commercial fell 3 percent, and with data centers removed it would be down 14.9 percent. For a sitework contractor, that is a map of where the next two years of work comes from.
Planning data is worth more to a materials buyer than spending data, because it arrives a year earlier.
The situation
Dodge Construction Network released the September Dodge Momentum Index on October 7. The index rose 2.4 percent for the month to 288.0, from a downwardly revised August reading of 281.3 (Source: Dodge Construction Network, September 2026).
The DMI measures nonresidential building projects entering the planning stage and historically leads nonresidential building spending by twelve to eighteen months. It is a forward indicator, which is exactly what makes it useful for deciding which bid lists to get onto.
The two halves
Institutional planning rose 9.4 percent for the month and 17.2 percent over the year, led by education, healthcare and government buildings.
Commercial planning fell 1.3 percent for the month and 3.0 percent over the year.
With data centers removed, the commercial segment would be down 14.9 percent from year-ago levels.
Dodge Construction Network · September 2026
That last figure is the one to sit with. Commercial building planning, setting aside a single category, has contracted by close to a sixth over twelve months. The growth in nonresidential building is institutional, and the margin is not narrow.
What institutional work means for an earthwork contractor
The sitework share is high. School and hospital campuses carry large parking fields, fire lanes, drives, detention ponds and long utility runs relative to building footprint. The material mix skews toward flex base, select fill and pipe embedment rather than anything specialty.
The buying process is different. These owners are bond-funded and publicly bid, on published schedules, with qualification requirements. That is a barrier the first time and an advantage every time after.
The timing is the opportunity. Planning leads construction by a year or more, which means the moment to get qualified and onto bid lists is while the projects are still in planning, not when they hit the street.
Where this connects to Texas
The largest institutional projects entering planning in September were hospital additions in North Carolina and South Carolina, so this particular month’s headline projects are not Texas ones. The signal is the category trend rather than the individual jobs, and Texas school and healthcare construction is driven by local bond programs on their own timetables.
The honest caveat
The DMI is national, and it counts projects entering planning, not projects that will be built. Plans get shelved, scopes get cut and timelines slip. A national planning index does not promise any specific package in any specific county. Use it to decide where to aim, not what to bid.
The forward read
If institutional planning keeps running at this rate while commercial stays soft outside one category, the contractors who spend this winter getting qualified on public work will have a materially different bid list in 2028 than the ones who do not. The labor side of that equation is worth reading alongside it.
Commercial without data centers is down almost a sixth. Institutional is up seventeen percent. That is the map.
Call 214-282-7980 or request a quote at aggregatesnow.com.



