The Backlog Number Is Carrying Somebody Else’s Work

Backlog rose to 8.7 months, but data center contractors are sitting at 11.3 and most mid-sized firms are not in that work.
Excavator and dozer parked at the edge of a partially graded Texas commercial site at end of day.

Construction backlog rose again in September, reaching 8.7 months. That sounds like straightforwardly good news until you see who is holding it. Contractors with data center work are sitting at 11.3 months, three full months above everyone else, and data center work is concentrated almost entirely among firms above $100 million in revenue. If your own backlog did not grow this quarter, you are not misreading the market. You are in a different part of it.

An industry average is only useful if you are near the middle of it.

The situation

The Associated Builders and Contractors Construction Backlog Indicator reached 8.7 months in September, up 0.2 months from August and up 0.2 months from a year earlier. The reading comes from a member survey conducted September 21 to October 5 (Source: Associated Builders and Contractors, September 2026 reading).

That is the second consecutive monthly increase, and on its face it says the industry is busy.

The 15 percent of contractors under contract on data center work averaged 11.3 months of backlog, three months more than everyone else.

Associated Builders and Contractors · September 2026

Who is actually holding it

About 15 percent of ABC members are currently under contract on data center work. Those members averaged 11.3 months of backlog. That is three full months above members without it.

And that work is concentrated by size. Thirty nine percent of contractors above $100 million in annual revenue report data center work. Among contractors below $100 million, it is roughly one in ten.

Most Texas sitework, utility and civil contractors in the five to one hundred million dollar range are in the second group. Which means the headline backlog number is substantially describing a tier above them.

What else is in the release

Two things worth as much attention as the headline.

More than one in four contractors expect profit margins to contract over the next six months, the highest share since November 2025. Sales expectations fell to an eleven month low.

By sector, commercial and institutional backlog rose to its highest level since July 2025, while heavy industrial backlog fell to its lowest since March, though it remains half a month above where it was a year ago.

Why the margin pessimism is not just mood

Put it next to the producer price data released this week, where final demand construction was flat for the month while steel mill products ran up 27.6 percent over the year. Contractors expecting compression are not being gloomy. They are reading their own input invoices.

What it means practically

Backlog is the wrong number to manage against right now, because the version of it in the headlines belongs to a segment most of our customers are not in. Mix is the better question. Know which categories you are actually exposed to, and know what you are assuming for inputs in each.

The honest caveat

ABC’s survey is a national sample of its own membership, which skews commercial and industrial and is not a Texas heavy civil panel. The direction and the internal splits are informative. The absolute month count is not a benchmark any individual contractor should measure themselves against.

The forward read

If commercial and institutional work keeps climbing while heavy industrial softens, the contractors positioned for site packages on commercial and institutional projects are the ones with room to grow into. That is a different bid list than the one that worked in 2024.

Do not benchmark yourself against a number that belongs to somebody else’s backlog.

Call 214-282-7980 or request a quote at aggregatesnow.com.

Ready to Order

Get a Delivered Number Before You Lock the Budget

One call covers sourcing, trucking and the delivery schedule. 24-hour quote response.

Delivered Pricing

Need a Delivered Number This Week?

Material, trucks and the delivery schedule in one call. 24-hour quote response.

214-282-7980Request a quote online

Run the Numbers

Materials Calculator

Work out tons and loads before you call.

Use the Calculator

Market Intelligence

Get the Weekly Brief

Market updates, material availability, and Texas construction intel. Published weekly for contractors.

Market Intelligence

Get the Weekly Brief

Texas construction and material market updates for contractors. One email, Wednesday mornings.